Wednesday 10 December 2014

River course work

We've been getting on with a few tasks on the river course this week.  The last of the scots pines between the 3rd and 4th holes that were killed by salt water flooding have been felled.  Work is in progress on slightly raising, extending and strengthening the bund on our boundary left of the 6th green.  It should now protect this area from all but the very highest surge tides.  Work has also started on building a couple of low mounds between the 8th and 9th holes.  The main purpose of these is to encourage players on the 8th to aim slightly left so that fewer balls are hit towards the 9th carry.

Danny felling the last couple of pines

Working on the bund left of the 6th

Starting work on the mounds

Arthur and Shane laying turf on one of the mounds right of the 8th

No comments:

Post a Comment